Journal of Light Construction - April 1994

On the Beach: Coastal Construction ( part 4 )

by Patricia McDaniel Hamilton

Figure 4. Because homes on pilings are typically quite tall, highlifts are indispensabletimesavers when it comes to moving materials.

Sheathing
We use 1 /2-inch minimum APA-rated structural sheathing, following the engineer's recommended nailing pattern - typically 8-penny nails on 3-inch centers at the edges and 12-inch centers in field. With multistory houses, the plan often calls for lapping the plywood over the band joist, tying the studs below to the studs above. If the plywood breaks right at the band joist, metal straps like the Simpson LFTA are needed to transfer the uplift loads from studs above to studs below.

All plywood edges need to fall on solid blocking for maximum shear strength. We sometimes have to build interior shear walls as well. For interior shear walls, we've found that plywood or let-in 1x4 bracing provides much stiffer wall sections than using metal bracing. In some cases, we add shear walls beyond what the specs call for. Houses on pilings have a peculiar and disturbing way of shaking or vibrating. Traffic on the steps or breezy days make the house seem to shimmy. It's better to write a change order sooner for additional bracing than to deal with seasick owners after they move in.

Figure 5. Metal connectors help resist the huge uplift forces coastal homes are subjected to. Hurricane connectors secure joists to girders, strap ties connect first-floor studs to second-floor studs, and rafter hold-downs tie rafters to top plates and studs.

Up on the Roof
By the time the house is ready for the rafters, the structure is often quite tall. Local codes limit the height of the house to 35 feet measured from the flood elevation to the midpoint of the main roof. Windy days can be dangerous when you're walking plates 30 feet up, so we usually allow some extra down time in the schedule for houses more than two stories tall.

Roof framing is mostly conventional. Once again, metal framing connectors are needed to secure each rafter to the studs below. If the rafters don't align with the wall plates, two connectors are needed - one to tie the rafter to both top plates and one between the top plates and stud. So we try where possible to align the studs with the rafters. Since stud spacing is usually on 16-inch centers, framing the roof 16 inches on-center means fewer connectors of a lower capacity.

Our typical rafter tie is a Simpson H7, which must be installed before sheathing the roof. If loads are concentrated by dormers or other roof openings, special consideration is given to concentrated uplift loads. In general, uplift loads from high winds are usually figured at about 1,000 pounds per rafter. Concentrated loads (at hip rafters or girder trusses, for example) can run into thousands of pounds, meaning custom hardware may be required.

Roof sheathing installs normally (once you wrestle it 40 feet in the air), but once again careful attention must be given to nailing patterns.

Weatherproofing
Making a house weathertight is difficult in an oceanfront environment. Along our part of the coast, "Northeaster" storms blow through about once every two weeks, bringing heavy rains and winds around 80 mph. It's an understatement to say we have to pay careful attention to caulking and flashing details to prevent leaks. We use Typar housewrap, lapping it from the bottom up and taping all the joints. Typar holds up extremely well to the wind and weather, and the gray color is easy on the eyes (when you're building along the beach, you don't need any added sources of glare).

Windows. We use only the highest-quality windows, preferably aluminum clad. We prefer to use at least Grade 60 windows, as rated by NWWDA (National Wood Window & Door Assn.). These are usually casement or awning type. When the client insists on double-hungs, it's necessary to settle for Grade 40. In addition, the cladding and hardware must be rated for seacoast exposure.

We always bed the window flanges in caulk, then tape them to the Typar with housewrap tape. We back all exterior trim at windows and doors with tar paper and use drip cap flashing above (Figure 6).

Storm shutters. Since we are building in a hurricane zone, we recommend that all coastal houses include storm shutters. The three basic types available are hand-applied modular panels, roll-down shutters, and folding (accordion) shutters. These are all engineered shutters. None of them is aesthetically pleasing, although roll-down shutters can be hidden in soffits.

For any of these shutters, an extra layer of trim is needed around windows and doors so that the shutter isn't obstructed by the window frame or hardware. With sliding glass and outswinging doors, you have to clear the door handle. Screen doors can also be a problem. This is best thought through early in the design to avoid reworking the trim later.

Figure 6. Coastal builders must take special care to seal openings against wind-driven rain. To install a window (left), the housewrapped opening is first covered with tar paper. The window is then installed in a bed of caulk. The author uses only clad windows rated for coastal conditions. The author recommends storm shutters (right) for all coastal homes to prevent hurricane winds and flying debris from bursting the glass in windows and doors.

Utilities. Utilities need to be elevated above the base flood elevation or somehow protected from inundation. Hvac units are usually built on separate, elevated decks, and electrical meters and panel boxes may be mounted higher than normal.

Closing in underneath. Many communities require that pilings be enclosed. Depending on the budget, we may box in individual pilings with siding and trim or enclose the entire perimeter with lattice or spaced 1x4s. In a traditional home, the crawl-space insulation can be left exposed, but for a piling house it is necessary to install a ceiling underneath. Our usual choice is a 3/8-inch roughtex plywood, although if there are car-ports or parking areas below the house, we sometimes use exterior gyp-sum. In crawlspaces, we choose materials for durability with less concern for aesthetics, typically 3/8-inch CDX or OSB.

Cost Considerations
The overall expense of placing a house on a piling foundation runs between $5 and $10 per square foot higher than placing the house on a concrete block crawlspace. The added expenses include the pilings, girders, bolts, cross-bracing, crawlspace ceiling, lattice enclosure, additional framing expense, and equipment rental.

Patricia Hamilton is co-owner and operator of Boardwalk Builders in Rehoboth Beach, Del. Photos by the author.


Return to Articles Index