Journal of Light Construction - April 1994

On the Beach: Coastal Construction ( part 3 )

by Patricia McDaniel Hamilton

Bracing. Cross-bracing at the pilings is necessary to resist lateral loads from wind or water (Figure 3). Once again, we let the engineer do the head scratching. If pilings top out any more than 2 or 3 feet above grade, we usually need 3x8 or 3x10 treated timbers bolted to the pilings in an X pat-tern, with two 3 /4-inch bolts at each connection.

Cross-bracing is easiest to install with one brace on each side of the pilings. This makes a very thick brace/piling sandwich. Unfortunately, if the area below the first floor is to be enclosed or partitioned, the cross-bracing may conflict with wall locations. Sometimes the two pieces can be installed on the same side of the pile, and half-notched into each other. This detail needs to be carefully considered at the design stage. Even with bracing in place, a piling foundation is not an absolutely rigid structure. When concrete slabs are poured around the foundation, expansion joints are needed at each piling.


Figure 3. Bolted two-by X-bracing (top) and interior shear walls (above) help stiffen houses built on pilings. Both details must be engineered.

First-Floor Platform
Layout and installation of floor joists is the next step. A "highlift" (four-wheel drive, extendible forklift) can be a real timesaver in this and subsequent steps, especially if the house is more than one story. We cut joists to length on the ground, then lift them in groups onto the beams.

Because the girders are rarely directly below the exterior wall lines, and may be slightly out of parallel, the trick is to securely fasten the joists to the band joist but only tack them to the girders. Then, when all the joists are in place, we can square the whole floor and then fasten the joists to the girders. Each joist/girder connection needs a hurricane tie (actual loads engineered) like the Simpson H6 (Simpson Strong-Tie, 4637 Chabot Dr., Suite 200, Pleasanton, CA 94588; 800/999-5099). It is easiest to install hurricane ties before the subfloor is installed, though they can go in later. We use only corrosion-resistant fasteners and hot-dipped galvanized nails. If the metal straps were galvanized before fabrication, all the edges will begin to corrode immediately. We field paint all such straps with a cold galvanizing compound, available in spray cans. Other options are stainless steel or Simpson's new Z-Max fasteners with triple zinc coating.

Framing continues in a conventional manner upwards from the first-floor deck, but special attention must be paid to point loads and to bracing the structure against wind loads. We frame standard stud walls, except that plywood is installed after the walls are raised. We always follow the engineer's plan for stud size and spacing.

Gable ends are best framed with continuous studs. This avoids a weak hinge point at the ceiling line. For cathedral ceilings, this detail is required. For extremely high ceilings, it is sometimes necessary to increase the stud size to 2x8 or larger. Double top plates are standard, and we take special care to stagger the laps and to secure the plates to the studs.

Continue to Coastal Construction Part 4

Return to Articles Index