Journal of Light Construction - April 1994

On the Beach: Coastal Construction ( part 2 )

by Patricia McDaniel Hamilton

Building the First-Floor Deck
Houses built on pilings are in essence hybrid post-and-beam houses. Ultimately, all loads must resolve to the pilings by way of beams, girders, and cross-bracing. Because of the complex load paths involved, and the likelihood that the home will be tested by high winds, water, and impact from waterborne debris, it is essential that the entire structure be engineered. Although we can design very simple houses ourselves in accordance with the SBCCI Standard for Hurricane-Resistant Residential Construction (formerly called Deemed to Comply), larger houses typically require an engineer familiar with the unique demands of coastal areas.

Figure 2. The gas-powered chain saw is the weapon of choice for notching pilings (above). Girders are tacked in place for drilling the bolt holes (below). The author likes treated Parallam girders (further below) because they come in long lengths, making them quicker to install than built-up girders.


Girders. The foundation girders - treated Parallams or built-up treated 2x12 beams - are attached to the pilings with bolts (Figure 2). These connections must be engineered. The piling should be notched only deep enough to provide a shelf for the beam to bear on, while still leaving at least 50% of its cross-section for securing the bolts. If the piling is cut flat instead of notched, steel straps are usually required to secure the beams to the pilings.

Notching. As a practical matter, laying out and cutting flat notches in round piles while working 6 to 10 feet above grade can be extremely difficult. We build a working platform by nailing framing lumber from piling to piling about 3 feet below the final top elevation of the poles, and use walk planks and guardrails where necessary.

The gas-powered chain saw is the tool of choice for cutting pilings. Sharp chains are essential. We usually have to resharpen the chain about every 20th piling. And though it's easy to forget, we try to avoid placing the saw in the sand.

The first cut establishes the top of the piling. We always mark and cut each piling 3 /4 inch below the elevation of the bottom of the floor joist to make it easier install the crawlspace ceiling in later stages of the project. The next step is to establish the house corners and girder lines on the tops of the pilings. We use conventional batter boards and string lines for this, and extend the corner point up to a block nailed to the top of the piling with a plumb bob. The outer pilings are usually placed 6 to 12 inches in from the edge of the footprint. At outside walls, we cantilever the floor joists 3 1 /2 inches beyond the girders. This leaves us plenty of room to attach enclosure walls or lattice below to enclose the girders - a zoning requirement in some communities.

After establishing the corners, we establish a string line for each row of pilings. The layout marks for the notches at each piling are then measured from the string lines. The girder lines sometimes need to be adjusted slightly to ensure adequate bearing at each piling. Once the line is established, we snap it across the tops of the pilings.

Next, we locate the seat of each notch with a transit. After marking out the notch cut, it's then a matter of holding the chain saw steady enough to create a flat, plumb vertical cut and a smooth, level horizontal cut. It takes care not to overcut. Although it might seem easier to simply flat-cut the tops of the pilings and use metal straps to secure the girders, this entails the added cost of additional bolts and metal straps, plus the added labor of drilling the extra bolt holes and cut-ting flat sections on the sides of the pilings for the metal straps. However, there are occasional pilings where this detail cannot be avoided - where girders meet at corners, for instance. Once the pilings are notched, the beams can be bolted on. We tack or clamp the beams in place on the pilings for drilling. Drilling one-inch- diameter holes through 12 or 14 inches of piling and girder is no pic-nic. A 1 /2-inch or 3 /4-inch electric or air-powered drill is required. An air-powered drill is expensive but less dangerous to use, because there's no kickback from torque when the bit seizes in the hole.

We typically use two 3 /4- or 7 /8-inch bolts at each piling/girder connection. If two girders meet at their ends on a piling, each one needs two bolts. With built-up 2x12 beams, we overlap at joints. Though they're more expensive, Parallams are easier to install because one continuous beam can run the length of the house. On occasion, concentrated loads will dictate the use of Parallam beams, or sometimes even steel I-beams. Steel beams and flitch plates have to be protected from corrosion, of course, by hot-dip galvanizing.

Continue to Coastal Construction Part 3

Return to Articles Index